22.
									
										You are handling a time-bound project. During the project review meeting, you find that the project is likely to get delayed due to lack of cooperation of the team members. You would ......
									
								
															
														
																									
										A:
											Warn the team members for their non-cooperation
									
																										
										B:
											Look into reasons for non-cooperation
									
																										
										C:
											Ask for the replacement of team members
									
																										
										D:
											Ask for extension of time citing reasons
									
																								 
							
																
									The answer is:
										B